During the assessment phase of migrating an on-premises Windows Server 2016 to Azure using Azure Migrate, you notice that the on-premises server has a high CPU utilization during peak hours. What is the best course of action to ensure a smooth migration process?

Answer Options

A
Disable all services on the on-premises server to reduce CPU usage.
B
Optimize the workload by reducing the load or scheduling tasks during off-peak hours.
C
Increase the number of cores on the on-premises server to match the expected Azure VM size.
D
Migrate the server to Azure during the peak hours to test the performance.

Correct Answer

B: Optimize the workload by reducing the load or scheduling tasks during off-peak hours.

Explanation

The correct answer is B because it addresses the issue by optimizing the workload before migration. Option A is incorrect as it does not address the current workload issue. Options C and D are not directly related to the current problem and might complicate the migration process.