SC-300 Practice Question 3496
Exam: SC-300
Domain: Plan and automate identity governance
Difficulty: medium
In PIM, what is an Alert that warns administrators about excessive permanent privileged assignments in the directory?
Answer Options
A
Alerts on excessive permanent assignments or missing MFA for activation
B
Alerts when client computer CPUs exceed 80% utilization
C
Alerts when toner levels in office printers are low
D
Alerts when users send emails with animated GIFs
Correct Answer
A: Alerts on excessive permanent assignments or missing MFA for activation
Explanation
The "Roles don't require multi-factor authentication for activation" or "There are too many Global Administrators" alert in PIM flags security risks for administrator review.